First thermocouple design completed - 4/3/01

Final thermocouple design completed - 9/28/01

Original solenoid design completed - 4/22/01

Final solenoid design completed - 10/5/01

Final software completed - 10/21/01

Project integrated - 10/22/01

First hour long test of final project - 10/28/01

First 24-hour long test of final project - 11/4/01

Final testing completed - 11/29/01

Poster presentation- 12/4/01

Final oral presentation - 12/6/01

 