The Terminators
 |
 |
 |
 |
| Eduardo Pineda |
Jovan Saenz |
Oscar Gonzalez |
Rafael Gonzalez |
Objective
The objective of our project is to design and implement a bottling machine with
a monitoring system.
Abstract
The project that was proposed is an automated bottling machine with a user
interface for monitoring the status of production. That is, the user interface
allowed the user to keep track of how many items have been bottled and thus
supervise the position of every piston. Hence, the machine was responsible for
filling and capping a 20-oz Power-aid plastic bottle. This process was composed
of three stations: station 1 consisted of positioning the bottle on the
conveyor, station 2 consisted filling the bottle with water, and finally in
station 3 the bottle was then capped. As a result, the entire bottling process
was automated and therefore controlled by a user interface that was used for
making sure that every piston was properly extracted or retracted. Furthermore,
the maximum cost of the machine was $6,500 dollars and was built and fully
operational by April 2001. The estimated time for filling each bottle was
approximately 10 seconds and the volume for each bottle was 600ml. The bottling
machine, however, was controlled by a Micrologics 1000 PLC (Programmable Logic
Controller).
Method of Completion
The method of completion that was used for this project basically consisted of
incorporating 3 engineering disciplines, Electrical, Mechanical, and Computer
Engineering. For instance, the Electrical aspect of the project will consist of
using a PLC(Programmable Logic Controller) to control the operation of the
bottling machine, electrovalves for controlling the actuators, and a surge
protector for ensuring that the machine does not suffer any overloads.
Therefore, in order to control the pneumatics and electrovalves the PLC
therefore had to be programmed using a software known as Micrologics.
Nevertheless, a surge protector was designed in order to prevent the machine
from short circuiting. The Mechanical aspect of the project, however, consisted
of designing the overall structure of the bottling machine. That is, the design
of the machine was sketched using such drawing tools as Solid Works 2000 and
AutoCad. Therefore, once the sketches were completed the machine was then ready
for assembly. The assembly process, however, required a great deal of attention
since any error in the connection of the components can result in a expensive
disaster. Finally, for the computer aspect of the machine a user interface
system was used for keeping track of the performance and production of the
machine. Therefore, the interface was responsible for displaying such
information as the number of produced items, and position of every piston.
Issues
One of the most important issues related to the project was the shortage of
funds. This was a critical part of the project because most of the pneumatic
parts of the project tended to be relatively expensive. In fact, it was
estimated that the overall cost of the project would reach a cost of
approximately $7,000.00. Furthermore, time was another issue that needed to be
addressed. That is, the construction of the machine, as composed of the frame and
conveyor belt, would require a sufficient amount of time since their
construction depended on a machine shop. Lastly, there was also the issue of
modifying certain parts of the machine such as the linear actuator and the
rotary actuator which were used for the capping process.
SolidWorks 2000 Drawings
Bottling Machine
The Feeding System
Photographs of Bottling Machine
Bottling Machine Photo
The Electrical Layout
The Bottling Process
The Capping Process
The Interface
Interface
The Visual Basic Intro Form
Visual Basic
Conclusion (or Current State of Project)
The project intended was the design and implementation of a bottling machine
with a user interface. The bottling machine was composed of 4 stations. The
first station of the bottling machine for instance was the feeder. The feeder as
the name suggest was basically rack where the bottles rested before the
initialization of the bottling process began. Once the process was initialized,
the bottles were then fed to a conveyor belt or station two of the process where
they were filled with water. After the bottles are filled with water, they were
then sent to station 3 where a bottle cap was placed and fastened to the mouth
of the bottle. Finally, station 4 was composed of the actual screwing of the
cap. Nevertheless, the entire process was thus controlled and operated by a
laptop computer. That is, the performance of the bottling machine was made
viewable to the technician and or manager through the use of an interface which
continuously displayed the number of processed bottles and the position of the
pistons. Furthermore, a database using Visual Basic was also designed to display
such information as the mechanical design, electrical design, utilities, and
interface. As a result, the project required a great deal of knowledge in the
engineering disciplines of Electrical Engineering, Mechanical Engineering, and
Computer Science.